1. The name and outline of the construction project

1. Name of construction project: Phase II project of comprehensive utilization of dilute sulfuric acid

2. Construction unit: Hunan Yicheng Technology Co., Ltd.

3. Project Overview

Hunan Yicheng Technology Co., Ltd. produces dilute sulfuric acid as a by-product. Dilute sulfuric acid is often unsalable, causing the company to stop production and seriously restricting the survival and development of the company. In order to solve this bottleneck problem, Hunan Yicheng Chemical Co., Ltd. The second phase of the comprehensive utilization of dilute sulfuric acid will be constructed by using the existing idle workshops to produce magnesium sulfate. The investment of this project is 3 million yuan, and a new magnesium sulfate production line is added, and the designed production capacity of magnesium sulfate is 2,000 tons. It consists of production workshop (including raw material stacking area and finished product stacking area) and environmental protection projects. The power distribution room, water supply and office facilities rely on the existing projects, and the drying heat utilizes the heat released by the synthesis of SO2 in the existing projects. The project is in line with the national industrial policy, and the construction of the project is conducive to promoting local economic development and environmental protection.

2. Working procedures and main contents of environmental impact assessment

1. Study the national legal documents and other documents related to the construction project, and preliminarily determine whether the project is feasible;

2. Screen key evaluation projects;

3. Carry out preliminary engineering analysis and environmental status investigation, and determine the work level of each individual environmental impact assessment;

4. Further engineering analysis and environmental status investigation;

5. Environmental impact forecast;

6. Evaluate the environmental impact of construction projects;

7. Put forward environmental protection suggestions and measures, draw conclusions, and prepare reports.

3. Main matters for soliciting public opinions

1. Satisfaction with the current environmental status of the area where the proposed project is located;

2. The main problems currently existing in the area where the proposed project is located;

3. What opinions and suggestions do you have on the construction of this project?

4. The main ways for the public to express their opinions

1. Written opinion; 2. Telephone feedback.

5. Environmental Impact Assessment Agency

Hunan Zhiyuan Environmental Consulting Service Co., Ltd.

6. Contact information

Construction unit: Hunan Yicheng Technology Co., Ltd.

Mailing address: Phase II Project of Comprehensive Utilization of Diluted Sulfuric Acid

Tel: 13762646786

Contact: Mr. Li

 

Hunan Yicheng Technology Co., Ltd.

June 10, 2019